Knock Down Rebuild Timeline: How Long Does It Take?
A knock down rebuild is a multi-stage project that typically takes 8–14 months from start to finish. This guide breaks down each phase so you know what to expect.
One of the most common questions homeowners ask is: how long will my knock down rebuild take? The answer depends on several factors, but here's a realistic timeline.
Phase 1: Feasibility & Planning (4–8 weeks)
Before any work begins, you'll need to:
- Engage a KDR builder for a site assessment
- Finalise your floor plan and inclusions
- Obtain preliminary cost estimates
- Arrange financing (construction loan pre-approval)
Phase 2: Demolition (1–2 weeks)
Once approvals are in place, demolition is relatively quick:
- Utility disconnections: 1–3 days
- Asbestos removal (if required): 2–5 days
- Structural demolition: 1–2 days
- Site clearance: 1–2 days
Phase 3: Design & Council Approvals (8–16 weeks)
This is often the most variable phase:
- Finalising detailed design and engineering: 2–4 weeks
- Lodging development application: 1 week
- Council assessment: 6–12 weeks (faster with CDC/complying development)
Phase 4: Construction (6–12 months)
Construction follows the standard new home build timeline:
- Slab and earthworks: 2–4 weeks
- Frame: 2–3 weeks
- Lock-up (roof, windows, brickwork): 8–16 weeks
- Fit-out (plaster, kitchen, bathrooms, fitings): 10–20 weeks
- Practical completion and handover: 2–4 weeks
Phase 5: Handover (1–2 weeks)
After the practical completion inspection and any rectifications, you receive the keys.
Total Timeline Summary
| Phase | Duration |
|---|---|
| Feasibility & planning | 4–8 weeks |
| Demolition | 1–2 weeks |
| Design & approvals | 8–16 weeks |
| Construction | 6–12 months |
| Handover | 1–2 weeks |
| Total | 8–14 months |
Factors That Can Delay Your KDR
- Council delays — complex applications or objections from neighbours
- Weather — heavy rain can delay slab and earthworks
- Material shortages — supply chain issues can extend construction
- Design changes — variations during construction add time
- Site issues — unexpected rock, poor soil, or contamination
Frequently Asked Questions
A knock down rebuild typically takes 8–14 months total: 4–8 weeks for planning, 1–2 weeks for demolition, 8–16 weeks for approvals, and 6–12 months for construction.