Overview
One of the most important — and most misunderstood — concepts in a new home contract is the difference between a genuinely fixed price and a contract that contains provisional sums or prime cost items that can increase after signing.
Many buyers sign what they believe is a "fixed price contract" only to receive variation notices during construction for site costs, engineering requirements, or selections choices that exceed the allowances in the contract.
Watch Out
Fixed Price Contracts
A true fixed price contract means the builder commits to complete the agreed scope of work for the agreed price — no increases unless you request changes (variations) or an agreed cost-escalation clause applies.
In practice, a genuinely fixed price contract can only exist when:
- ✓A soil test has been completed and the site classification is known
- ✓Engineering assessments have been done
- ✓Your selections (tiles, flooring, appliances, etc.) are finalised
- ✓All provisional sums and prime cost items have been converted to fixed amounts
Most building contracts at the time of signing do not meet all of these criteria — which is why provisional sums are common.
Provisional Sums (PS)
A provisional sum is an estimated cost for an item or area of work where the final price cannot be determined at contract signing. The builder provides a best-estimate figure, but the actual cost is adjusted (up or down) once the work is completed.
The most common provisional sum items in new home builds are:
- Site costs / earthworksThe biggest and most common PS that blows out. Depends on soil class, rock, slope, fill, and drainage.
- Service connectionsCost to connect to power, water, sewer, and gas. Can vary significantly by lot location within an estate.
- Council requirements / engineering variationsUnexpected engineering upgrades (retaining walls, additional footings) triggered by council or inspections.
- Demolition (knockdown rebuilds)Demolition costs depend on what's found — asbestos, footings, trees.
Tip
Prime Cost (PC) Items
A prime cost item is a budget allowance for a specific supply item — such as a tapware set, tiles, or light fittings — where the buyer hasn't yet made their selection. The contract includes a PC allowance (e.g. "$800 PC for kitchen tap set"), and the actual cost is compared to this allowance at selection time.
If you choose a product that costs less than the PC allowance, you receive a credit. If you choose something more expensive, you pay the difference. Prime cost allowances are often set conservatively — meaning you may find that most available options exceed the allowance.
Watch Out
What to Look for in Your Contract
Before signing any new home contract, ensure you or your solicitor have:
- →Identified every provisional sum and prime cost item
- →Confirmed what soil class/category the site cost PS assumes
- →Asked for the builder's site cost experience on similar lots nearby
- →Confirmed what triggers variations to provisional sums
- →Asked what the realistic high-end scenario for site costs is
- →Confirmed that 'fixed price' is defined in the contract (not just marketed)
- →Had the contract reviewed by a solicitor experienced in building contracts
Varies by Builder
Site Costs Provisional Sum
The most significant variable in most new home builds. Confirmed only after engineering assessment, soil test, and site survey. Can range from $5,000 to $50,000+ depending on site conditions.
Frequently Asked Questions
Frequently Asked Questions
Related Guides
Continue Comparing Builders
Planning a new home? Compare Australia's leading builders by inclusions, standard features and specifications before you sign.
Compare by State
Compare by City
Explore Estates & Services
Compare My Build
Compare Builders That Include This
See which builders include this as standard and where it may be an upgrade.