H1 vs H2 Slab Classification

What the H1 and H2 soil classifications mean for your slab, your build cost, and what your builder must include.

4 min·Compare My Build — Independent Resource· Updated June 2025

Introduction

Australia uses a site classification system (AS 2870) to categorise how reactive the soil is beneath a new home. The classification determines the type of slab required and directly affects your build cost. H1 and H2 are the two "high reactivity" classifications — both require more engineering than the standard M class site.

Key Differences

FeatureH1 ClassH2 Class
Soil reactivityHighVery High
AS 2870 movement40–60mm60–75mm
Typical slabReinforced raft slabHeavy raft or piered slab
Cost vs M class+$5,000 – $12,000+$10,000 – $20,000+
Common inMany QLD and NSW sitesExpansive clay soils, some SEQ
Requires engineerYes — specific designYes — more complex design

Pros and Cons

Pros
  • + Both classifications result in a properly engineered, structurally sound slab
  • + Modern H1/H2 slabs perform well when designed and built correctly
  • + Knowing your classification upfront avoids budget surprises
  • + Engineers design site-specific solutions for H1/H2 conditions
Cons
  • − H1 and H2 slabs cost significantly more than M class
  • − Many builder base prices assume M class — H1/H2 incurs extras
  • − Delays possible if geotechnical report is not ordered early
  • − H2 sites may require additional drainage or moisture management

Cost Comparison

Cost Comparison
M class slab (waffle pod)$8,000 – $14,000
H1 class slab (raft)$13,000 – $22,000
H2 class slab (raft/piered)$18,000 – $35,000+
Site classification report (geotech)$500 – $1,500
Always get a geotechnical report before signing a building contract. Slab costs can vary by $10,000+ depending on classification.

Common Builder Inclusions

Common Builder Inclusions
  • ›Most volume builder base prices are based on M class (flat, reactive) sites
  • ›H1 or H2 site upgrades are almost always charged as site costs on top of the base price
  • ›Some builders include an H1 slab allowance but not H2 — always check the contract
  • ›Site classification reports are usually the buyer's responsibility to arrange

Watch Out

Never sign a building contract without first knowing your soil classification. If the report comes back H1 or H2 after signing, you'll be required to pay additional site costs that weren't in your original quote.

Frequently Asked Questions

Continue Comparing Builders

Planning a new home? Compare Australia's leading builders by inclusions, standard features and specifications before you sign.

Compare My Build

Compare Builder Inclusions Side-by-Side

See which builders include more as standard — free, independent, no sign-up required.

Start Comparing Now