Provisional Sums Explained

What Provisional Sums are, why they vary, and why they're one of the biggest risks in a new home building contract.

5 min·Compare My Build — Independent Resource· Updated June 2025

Introduction

Provisional Sums (PS) are estimated cost allowances in your building contract for items where the full scope or cost is unknown at the time of signing. They are a normal part of residential building contracts — but they are also one of the most significant sources of budget blowout. Understanding how they work is essential before you sign.

Common Provisional Sum Items

PS ItemTypical PS AllowanceTypical Actual Cost
Site costs$5,000 – $10,000$10,000 – $40,000+
Rock excavation$3,000 – $5,000$5,000 – $25,000+
Retaining walls$5,000$8,000 – $30,000+
Service connections$3,000 – $5,000$5,000 – $20,000 (rural)
Landscaping$0 – $5,000$15,000 – $50,000+
PoolNot applicable$50,000 – $150,000+

Watch Out

Site cost Provisional Sums are the most dangerous. A builder may set a $5,000 PS for site costs when the realistic cost on a typical suburban block is $15,000–$30,000. The difference comes out of your pocket after signing.
Common Builder Inclusions
  • ›Review every PS item in your contract and challenge unrealistic allowances
  • ›Order a geotechnical report before signing to get a more accurate site cost estimate
  • ›Ask your builder: 'What is the average PS variation in your last 20 completed homes?'
  • ›Try to convert PS items to fixed prices wherever possible
  • ›Always budget a 15–20% contingency above total PS allowances

Frequently Asked Questions

Continue Comparing Builders

Planning a new home? Compare Australia's leading builders by inclusions, standard features and specifications before you sign.

Compare My Build

Compare Builder Inclusions Side-by-Side

See which builders include more as standard — free, independent, no sign-up required.

Start Comparing Now