Prime Cost Items Explained
What are Prime Cost items in a building contract, why they can blow out your budget, and how to manage the risk.
Introduction
Prime Cost (PC) items are placeholder allowances in a building contract for specific fixtures and fittings that you select later in the construction process. They are one of the most common sources of budget blowouts in new home builds — particularly when PC allowances are set unrealistically low, or when buyers select items above the allowance without budgeting for the difference.
Common Prime Cost Items in New Home Builds
| PC Item | Typical PC Allowance | Realistic Cost |
|---|---|---|
| Kitchen tapware | $200 – $400 | $400 – $1,200 |
| Bathroom tapware (per bathroom) | $300 – $500 | $600 – $2,000 |
| Floor tiles (per sqm) | $30 – $50/sqm | $60 – $200+/sqm |
| Light fittings (total) | $1,500 – $3,000 | $3,000 – $8,000+ |
| Kitchen appliances | $2,000 – $4,000 | $4,000 – $12,000+ |
| Door hardware (total) | $500 – $1,000 | $1,000 – $3,000 |
Common Trap
- ›Review all PC allowances in your contract before signing
- ›Compare PC allowances across builders — a lower base price with low PCs may be more expensive overall
- ›Make selections as early as possible to convert PCs to fixed specifications
- ›Ask your builder: 'What products are your PC allowances based on?'
- ›Budget 20–30% above total PC allowances as a contingency for selections
Frequently Asked Questions
Related Guides
Continue Comparing Builders
Planning a new home? Compare Australia's leading builders by inclusions, standard features and specifications before you sign.
Compare by State
Compare My Build
Compare Builder Inclusions Side-by-Side
See which builders include more as standard — free, independent, no sign-up required.
Start Comparing Now